MASTER PLANS
Phase 1

Click image for enlarged view.
Phase 1 will begin with Marlborough District Council’s construction of an artificial hockey turf at the site of the co-located colleges.
Once completed, the existing hockey turf at College Park will be removed to make way for the new intermediate campus.
Phase 2

Click image for enlarged view.

Click image for enlarged view.
Phase 2 is the longest construction phase, with the new intermediate campus and the first half of the co-located colleges’ campus being built. Bohally will relocate to the College Park campus once it has been completed.
Marlborough Girls’ College will move across to finished co-located spaces at the end of this phase.
Phase 3

Click image for enlarged view.
Once Marlborough Girls’ College has moved out of its existing buildings, construction will begin on the third phase to complete the Co-located College’s campus.
Marlborough Boys’ College will relocate to the campus at the end of this phase.